By Meraas · Dubai Holding · Dubai Design District · Three towers joined through their lobbies: A, ground and 30 floors (182 homes); B, ground and 37 floors (177); C, ground and 33 floors (198).

Price fromAED 2.03M
Homes1–4 Bed & Penthouses
Size range862 – 9,757 sq ft (average by type)
HandoverQ3 2030
Payment plan75 / 25
About this project

The Edit at d3 is three towers on the Dubai Canal waterfront of Dubai Design District, rising 30, 37 and 33 floors above ground and connected through their lobbies. Sky gardens are cut into each tower at several levels.

There are 557 homes: one- to four-bedroom apartments and three penthouses. On Meraas's plans every bedroom has its own bathroom and every layout a powder room. Average sizes run from about 860 sq ft for a one-bedroom to about 2,800 sq ft for a four-bedroom, with the penthouses near 9,800 sq ft.

Each tower takes a theme. Tower A holds the cinema, co-working and gallery space and a social club. Tower B is given to wellness, with the gym, yoga and wellness studios. Tower C is built around families, with family lounges and a kids' club. At ground level there is a resort-style family pool, a lap pool, a kids' pool and a padel court.

Completion is estimated for August 2030.

Family Pool & Lap PoolPadel CourtSky GardensSky LoungesCinema RoomGym & Yoga StudioKids' ClubCo-working & Gallery

Dubai Design District · Dubai Canal waterfront · three towers, 557 homes · completion August 2030

How we read it

The Edit is Meraas's second release on the d3 waterfront, and Meraas prices it against the first tower, which its briefing describes as a sell-out at the May 2025 launch. The briefing puts the average ticket within AED 0.2M of that first tower at every size, from AED 2.4M for a one-bedroom to AED 11M for a four-bedroom. If you missed the first release, this is the same district at the same money, four years from handover rather than three.

The district is the reason to look. On Meraas's figures d3 already has more than 1,100 offices and 20,000 people working in it, and is planned for 60,000 residents. It hosts Dubai Fashion Week and Dubai Design Week. Demand from people who already work there is the base a rental case needs.

Meraas's briefing also carries its own rental estimates, with yields up to 8.1% on a one-bedroom. We do not quote developer yields. We run our own on the unit you are considering.

The plan is 75/25: 20% on booking, 55% in six instalments to July 2028, and 25% at handover in August 2030. The August 2026 instalment has passed, so expect 30% at signing plus the 4% DLD fee. The honest position: 557 homes is a large release into one district, so a resale before handover competes with the developer's own stock.

Specification

Unit mix and specification

HandoverQ3 2030
Size range862 – 9,757 sq ft (average by type)
TypeSizeUnits
1 Bed862 sq ft avg · from AED 2.03M237
2 Bed1,314 sq ft avg · from AED 4.02M146
2 Bed + Maid1,450 sq ft avg54
3 Bed + Maid2,163 sq ft avg · from AED 7.71M98
4 Bed + Maid2,792 sq ft avg · from AED 10.7M19
Penthouse9,757 sq ft avg3
Pricing

Payment plan

  1. 20%On booking
  2. 10%August 2026
  3. 5%December 2026
  4. 10%May 2027
  5. 10%October 2027
  6. 10%March 2028
  7. 10%July 2028
  8. 25%On handover (August 2030)

75% through construction on dated instalments and 25% at handover, per Meraas's price sheet. Instalments already past their date fall due on signing. The 4% DLD fee is paid with the SPA.

Location

What is nearby

  • The Dubai Mall6 min
  • Downtown Dubai7 min
  • City Walk7 min
  • Business Bay10 min
  • DIFC12 min
  • Dubai International Airport15 min
Questions

Questions buyers ask about The Edit at d3

Who is the developer of The Edit at d3, and where is it?

The Edit at d3 is a Meraas Dubai Holding project in Dubai Design District.

What is the starting price at The Edit at d3?

Prices at The Edit at d3 start from AED 2.03M. Prices come from the developer and change with each release, so ask us for current availability.

What is the payment plan for The Edit at d3?

The payment plan is 75 / 25. 20% on booking, then 6 further instalments, 25% on handover (August 2030).

When is the handover at The Edit at d3?

The developer’s handover date is Q3 2030.